I'm designing a new double-deck layout to fit inside my 12x16 'train shed'.  It will have an 'outdoor' helix structure,... outside the main shed, but in its own enclosure.
%2C%20ps.jpg 

It will have shelf's on either side, and a peninsula. For the longest time I had been planning for a 6-8 track staging area to be located approx 8" under ONE of the side shelfs,...perhaps like this

Edited: removed an old track plan as it is way out of date, and replaced it with this newer version,..
s%281%29.jpg 
 

 

I decided to re-look at the possibility of utilizing the helix structure to gain access to the the staging tracks. What if I decided to try to add two loops to the bottom of my planned outdoor helix to take the trains down to the staging level?
 

And now I could have staging tracks on both sides of the layout  I could even have staging down the center of the peninsula. Lets see 6 tracks each on both sides, and 2-4 down the center,...wow, 14-16 tracks of staging (each with a different type train ready to run)

Brian

1) First Ideas: Help Designing Dbl-Deck Plan in Dedicated Shed

2) Next Idea: Another Interesting Trackplan to Consider

3) Final Plan: Trans-Continental Connector

Reply 0
railandsail

crepper or rolling seat

Perhaps I just need a half-creeper, or a pneumatic roller seat ?

Reply 0
railandsail

Angle Iron Brackets made from used Bed Frames

Quote:

TrainzLuvr

Let me show you what I mean...the black bracket below (top left) was the original design I started with which I actually saw here on MRH, from Bill Brillinger

 

@trainzluvr

I have now changed my plans, and intend to use some brackets somewhat like you illustrated that were fabricated from angle-iron. I had some 1.5" flange angle iron I salvaged from a metal storage shelf. but I only had just so much of that material, and not enough to make all the brackets I will need.

An Idea popped into my head. Why not just use some angle-iron that can be salvaged off of bed frame mattress supports. Those bed frames are made from some very strong metal that is just the size we need to make brackets,...and they are available real cheap at thrift shops or metal scrap yards.

 

 

Reply 0
Marc

Angled iron an T iron

 

I'm an iron worker here in belgium

The angled iron work fine,but I will suggest you to use a somewhat most ticker flat iron on which you solder it.

I also suggest you to make in the flat iron flange two holes on the upside over the angled iron, meaning, this flange is longer over  the flat bed of the angled iron, this give you a more  solid attach on the wall and the bracket can support more weight.

The space between the two holes must be like, the first at 2 cm from the angled iron, the second 8 cm over the first hole; the Under angled iron hole 3 cm under the angled base, flange is  somewhat like a 3 or 5mm flat iron thick by the width of your angled iron.

You must know it exist inegal angled iron, meaning the two side of the angle are not equals; one side of the angled iron has a greater side than the other.

Another solution is to use T iron in place of an angled one, with the flat bed over, they are also strong and the under flange will be smaller.

Drill many holes in the side of the angled iron, this will help to fix wire or everything else on the bracket, they are easier to do before you solder the parts.

Don't know the price of soldering work in the US but sure not  very expensive, if you give the already cut pieces and already drilled.

Here in Europe, lenght of flat iron or angled one come in lenght of 6 meters, this give you some bracket in a lenght.

If you need longer bracket, the tickness of the flat iron flange is important, his lenght on the top side of the angled iron and the need to put more hole to fix it on the wall.

By designing this kind of bracket you could  avoid the need of a strengthener under the bracket; I'm sure with a 5mm thick flat iron  flange with three hole over and a 40x40x5 angled iron in a lenght of 60cm spaced every 50cm  with a good fix on the wall, you could easily walk on the anchored benchwork.

Marc

On the run whith my Maclau River RR in Nscale

Reply 0
railandsail

Combo Bracket for both Main Deck and Staging Deck

@Marc
Thanks for your suggestions. BTW I am assuming when you said 'soldering' you meant our term 'welding'. We will be arc welding in a specific atmosphere. My friend, a contractor, will be doing the welding. I will be the 'lackey' doing all the prep work and cutting....ha...ha.

Our brackets for that lower area of track will be a combination bracket in that it will have an 'arm' at the top to support the main lower deck of my double-deck layout. It will also have an 'arm' about 8-9 inches lower that will support the staging level deck.

We have decided to make the bracket a little 'taller' than necessary so as to get a good 'grip' on the 2x4 stud with less tendency to load up and one fastener.

There will also be a feature that allows for an additional support leg be inserted at the outer end of the 'arm' that holds up the main deck, in case there is a need to climb up on that deck.

Reply 0
Marc

soldering is welding .....

Hi,

Sorry  of  the false use of words.

I speak English but technical words are somewhat else to learn and to use correctly in a discussion for me.

And in french Welding is "souder"; in french iron welding is "souder du métal" but also soldering a feeder on track is also "souder un fil au rail" in french.

In french only one word "souder" verso in English soldering or welding.

 

Yes arc welding or mig welding are sure excellent job to build your bracket.

If you have any more technical question I will do my best to help You.

Marc

 

On the run whith my Maclau River RR in Nscale

Reply 0
Marc

soldering is welding .....

Hi,

Sorry  of  the false use of words.

I speak English but technical words are somewhat else to learn and to use correctly in a discussion for me.

And in french Welding is "souder"; in french iron welding is "souder du métal" but also soldering a feeder on track is also "souder un fil au rail" in french.

In french only one word "souder" verso in English soldering or welding.

 

Yes arc welding or mig welding are sure excellent job to build your bracket.

If you have any more technical question I will do my best to help You.

Marc

 

On the run whith my Maclau River RR in Nscale

Reply 0
railandsail

Continous Staging Tracks rather than just Dead Ends

Quote:

By varying the short straight track sections prior to those multiple curves we can get greater spacing between their centerlines, and greater spacing down the 'fairway' (the straight track sections down the (each) side of the shed....)

s%281%29.jpg 

terlines.jpg 

Brian

My original idea was to have those 2 staging areas on either side of the room, consisting of 5 tracks each, simply extend to the end of the room and dead end there. Staged trains would be backed into each of those 10 tracks (5 tracks x 2 sides), ready to pull out forward and enter the staging access helix to go to the main layout track. That dead end of those tracks would be at the end of the room/shed opposite the helix end of the shed,...that is the door end of the shed.

The gentleman who is welding up my brackets ask me, "Why not make another removable bridge across the door entrance to join those two sides of the dead ended staging tracks. Then the trains could pull forward continuously thru the staging tracks?"

That's not a half bad idea. If I provided such a removable bridge between the dead ends of those 5 tracks down each side, it could offer the alternative to utilize the staging in such a fashion if so chosen in the future. I think I will provide that option.

Drawing to come.

Reply 0
ACR_Forever

If you pay careful attention to alignments

Brian

You'll never regret that connection, if it works well.  Restaging trains is one of my least-favorite activities, so if you can avoid it, I'd encourage that.  What elevation from the floor is it?

We've just installed a vertical lift gate on my layout - it will have a single track on each side, and lifts 22" to give anyone under 6' clearance.  So far, we've worked out the alignment of the track on both edges of one side; carefully aligned v-blocks under each end of the track, latched in place with cabinet hardware. 

Not sure if you want to get that extravagant, but I like the way the track cannot move.

The other side of the lift gate remains theoretical, but I think it will be done the same way; it's a bit more complicated, as it will incorporate a 3-span deck girder bridge, with the abutments and piers on the gate to ensure alignment of the bridge assembly. 

Blair

 

Reply 0
railandsail

Elevation & Bridges

@ Blair.

Height above floor for staging is about 32 inches,...8 inches under main deck at 40 inches.
Not sure what I am going to do about bridges across entrance to shed as there will likely be 3 levels, 1) staging level, 2) main deck level, then 3) upper deck of dbl-deck design.

Reply 0
railandsail

New Staging Drawing

Quote:

My original idea was to have those 2 staging areas on either side of the room, consisting of 5 tracks each, simply extend to the end of the room and dead end there. Staged trains would be backed into each of those 10 tracks (5 tracks x 2 sides), ready to pull out forward and enter the staging access helix to go to the main layout track. That dead end of those tracks would be at the end of the room/shed opposite the helix end of the shed,...that is the door end of the shed.

If I provided such a removable bridge between the dead ends of those 5 tracks down each side, it could offer the alternative to utilize the staging in such a fashion if so chosen in the future. I think I will provide that option.

Drawing to come.

Brian

As I said, drawing to come. Here is my current sketch.

%2C%20ps.jpg 

Sorry its of poor quality as I had to flash photo it indoors due to a whole day of cloudy, rainy weather here in 'sunny Florida'. I'll see if I can do better in the next several days.

 

Lets start with getting to the staging area(s). There is a track right next to the wall on the left hand side of the shed at the rear corner that enters the OUTSIDE curve of the track helix. It begins its descent inside the shed just after it crosses over that last major bracket supporting the main level deck. By the time it reaches the 9 o’clock position on the helix it is at a -1.5”. It subsequently drops 1” for each quarter turn around the helix, ending up at -7.5” at the 3 o'clock position, and subsequently -8” at the 3-way turnout at the entrance to the 3 area staging. That is a little less than a 2% grade (1.8% I believe).


Now it can branch out into 3 directions, ...5 tracks on either side, and an undetermined number down under the straight peninsula. At the head of each side track(s) there are 4 Peco medium radius turnouts that feed 5 tracks that ALL make the same 24” inch radius turn into the straight sections of the staging.

tches(1).jpg 
 

 

Those 10 straight sections (5 each side) of staging make turns at their 'tails', and can either dead end at the bracket that is located to either side of the big door, OR there will be a lift-out bridge provide that could connect the 5 tracks continuously. The radius’s on those staging track tails are progressively built in 24”, 26.5”, 29”, 31.5”, and 34” so as to maintain a 2,5” centerline between themselves. Other than in the 4 corners of the layout, the shelf depth required for these generously spaced staging tracks is only 14” from the wall.

 

The staging level deck will be constructed of the same 3/4” plywood I purchased for the main level deck, and will be supported every 24” by a combination of metal brackets fashioned from the same 2” square, and 1.5” angle iron I am planing on using for the main deck above it. That is probably 'overkill', and the staging areas may just utilize the angle iron material.


0plywood.jpg 



 

Not yet shown in this dwg is a central spine support down the peninsula built of the 2” square tubing to be very minimalistic yet strong.


The helix itself will be 'housed' in a trapezoidal shaped box formed on four sides using some 1.5” square alum sections I salvaged from some screened in porch/pool structure here in Florida. They will intersect with some 68” steel circles I am having bent up from 1.5” angle iron. Those two steel circles (one top, one bottom) will be joined by 12 vertical post made up from 1” square alum sections I salvaged elsewhere. It should be strong, and rigid.


lling_01.jpg 

F1155(1).jpg 

 

 

Alum siding will be attached to the outer perimeters of the framing and the top cover. There will be some sort of trap door in the bottom to keep pest out.

Reply 0
ACR_Forever

answers, and questions

Hi Brian

Firstly, you asked earlier how a 3-way could have two different radii.  Consider: these three way switches are actually a overlapped pair of normal switches, a left and a right.  There are two sets of points, one for each.  Each switch diverges from the straight-through route at a different point in the body of the turnout.  I just measured my Peco C100 medium 3-way.  Both diverging legs are 12 degrees from the main at the point the rail ends, and they have each diverged the same distance from the main.  The points for the left leg leave the main approximately an inch further into the switch than the points for the right leg.  If you have those three conditions, how can the right leg not be a larger effective radius than the left leg?  (I may have earlier stated that the right leg was smaller radius - my memory failed me again).

Now, about that switch ladder -

- Why only five tracks?

- Why not use a "" (jeepers, the word won't come to me right now), a ladder in which the heel of each switch is placed on the diverging leg of the previous one?  Given Peco's 12 degree divergence, four switches would rotate your ladder 48 degrees for you, bringing you to the tangent track much more quickly.  A fifth switch is easily inserted, and a sixth can be, depending upon the radii you want for the tracks leaving the three way; those would allow tracks six and seven in the staging yard, if you wanted them. 

If any of this is not clear, message me back and I'll do a quick sketch for you in CAD this evening.  Gotta go!

Blair

Reply 0
ACR_Forever

Pinwheel!

That's what the word is.  A pinwheel ladder. 

Reply 0
railandsail

A pinwheel ladder...wow

I'll have to take a closer look at this possibility.

Remember I sought to have all of those radiuses be no less than 24" .
And I was originally trying to keep the straight portions of the tracks as long as possible, not consumed by the curves.

 

 

Reply 0
ACR_Forever

Well,

I could draw a pinwheel over top of your original plan, to show the differences, if you wish.  But we're training tonight now, so it'll have to be drawn tomorrow sometime.

Let me know if that would help.  I do need to know the angles you've chosen for the ladder main relative to the yard body tracks in your plan.

later

Blair

Reply 0
ACR_Forever

Well,

I could draw a pinwheel over top of your original plan, to show the differences, if you wish.  But we're training tonight now, so it'll have to be drawn tomorrow sometime.

Let me know if that would help.  I do need to know the angles you've chosen for the ladder main relative to the yard body tracks in your plan.

later

Blair

Reply 0
railandsail

Alternative Drawing

Quote:

I could draw a pinwheel over top of your original plan, to show the differences, if you wish.  But we're training tonight now, so it'll have to be drawn tomorrow sometime.

No problem, I've got a lot of other things to work on as well.

Quote:

Let me know if that would help.  I do need to know the angles you've chosen for the ladder main relative to the yard body tracks in your plan.

That would be great, to have a look at the alternative.

I didn't chose any particularly angle(s) for the ladder. My only constraints were that the 3-way turnout was outside the shed,

1) and centered on the shed's interior centerline (5.5' feet, 5' 6" to either sidewall).
2) Next there had to be a minimum radius (24") turn from that 3-way to the ladder track.
3) Then it was the goal to get the outer track out to the very side of the shelf and make the turn into the straight trackage via a minimum 24" radius. 
4) This outer most staging track needs to be a minimum 3" from the wall of the sheld (edge of stage track shelf). then the goal was to have a minimum of 5 tracks, all with minimum 24" radius feeding them. .

5) I initially experimented with Peco smalls, but the found I could use Peco mediums, both Code100

Reply 0
ACR_Forever

how long

Is your room?  I see it's 11' wide, but front to back?

Blair

Reply 0
railandsail

Dimensions of shed.

Outside dimension 12x16
Inside dimension 11 wide x 15 long

BTW, on the straight tracks down the length of the shed. I had plans that the outer track (nearest the wall of the shed), the CL of that track would be 3" from the wall. All the rest would be on 2.5" centers. That would mean that 5 tracks could be handed by a staging shelf as little as 14 wide. Of course it could be wider if necessary, but I think 5  tracks down either side (total 10 there), plus 4-5 tracks down the center under the peninsula should be quite enough.

Sorry, been out of touch most of the day collecting up tools and paint for the job. And tomorrow morning I will be attending a train show in Deland FL. Not much hope for good things at this show, but I need a break.....ha...ha

 

PS: Blair,somehow I lost your private email

Reply 0
Guitarmike

Brian, You are a brave

Brian,

You are a brave man. 

I am 54 and have had 10 back surgeries. When I saw you pictures all I could think of was if that was mine every time a train would run into the helix it would get stuck on dirty track or derail, just so I'd have to keep crawling into the center of the helix. I would make two sides of the helix enclosure open with a door so I could access the stuck derailed train from the outside.

 

Mike

Reply 0
railandsail

Bigger Acess Door

I was discussing my helix idea with a friend and he suggested a bigger outside access door to that side of the 'helix box' close by my 3-way staging turnout, and the one other turnout in the helix. I thought it was a good idea, likely to incorporate it.

Reply 0
ACR_Forever

side access to helix

Brian

I'd be tempted to hinge at the corners whatever sheet material you're using as siding, so that all 3 sides are accessible.  Or, make them easily removable (corner screws only, or suitcase latches, whatever).  That may weaken the structure, but increases the chances of being able to fix derailments(Murphy's law says that if you do this, you'll never have a problem in an accessible area).  Besides, with side access, you can arrange to run the wiring bus and feeders vertically down one or more corners for easy access, which is a good thing to do.  I'm 57, and I'm learning to plan as if I won't always be as mobile as I am now - and that's one heck of a lot less mobile than I was at 27.  Plan for the worst, then you'll be pleasantly surprised.

Blair

Reply 0
railandsail

Helix 'BOX'

Quote:

I'd be tempted to hinge at the corners whatever sheet material you're using as siding, so that all 3 sides are accessible.  Or, make them easily removable (corner screws only, or suitcase latches, whatever).

I'll have to give that idea some more thought, as my siding will all be very light weight corrugated metal sheeting, and it will be attached to the square tubing that frames the 'box'. So the skins will not necessarily be load bearing.

But I would worry about water proofing and wind resistance.

Reply 0
ACR_Forever

Agreed

But those are details that should be manageable.  After all, you're "rail and sail" - you should be familiar with those, too!

Blair

Reply 0
railandsail

3 Zones of Staging

I haven't revisited this subject thread in quite awhile,...because I have been working on the plans, and the helix modification, and start of the helix construction.

For the moment I'll just post this drawing of the 3 zones of staging. There will be 5 tracks to either side of the room/shed. These will be mounted on a 12"-14" board of 3/4 plywood cantilevered off of a very substantial metal framework attached to the 2x4 studs of the shed.

Then there will be 5-6 tracks down the center under the peninsula.  These will be off to one side of, and cantilevered to 'metal frame spine' that will support both the peninsula main deck and this staging deck.

%20zones.jpg 

...more to come

Reply 0
railandsail

Helix, Staging Track

Quote:

Helix, Staging Track Access....error

Last night went to bed believing I had solved my problem with access to the staging tracks,.... via the use of another lower level addition to the helix structure.

This morning I woke up realizing I had forgotten to consider an important aspect. I can't have both the track feeding this downward spiral to the staging area, AND the bottom balloon loop track, entering the helix at the same height.

Back to the drawing board ! 
But, I am still a renewed fan of utilizing the helix to get to the staging tracks.

Just have to figure out the best way to enter this sub-helix?

Just ran across this older posting of mine where I was having problems figuring out how to have access to my lower level staging via the helix structure. I have now figured that out.

The track going down its portion of the helix structure to staging will start its downward path slightly before it exits the left hand rear of the shed, then proceed to utilize the outer loop of trackage to eventually dive under the level balloon loop occupying the inner trackage.

DWG to come