Oztrainz

Hi all,

I model a whole transportation system that is operated probably as prototypically as possible based on extensive research and given the technical impossibility of operating this transport system exactly prototyplcally. But for my transportation system there was no TT/TO, track warrant systems, no fixed signals or complicated train management system. Why?

Because the line was operated as "one locomotive in steam" - this meant that there was "nothing to hit" while the only operating locomotive was out there doing its stuff. Trains ran as often as the locomotive and its train could get from one end of the line to the other, and its train was swapped for another train going the other way. 

Is it likely that this layout of a transportation system will make much of an appearance here? So far, based on some of the comments I've received in various previous postings about the method of its build and logic behind how it was built as a sectional layout,  this is probably most unlikely.

After all, this layout is:

  • is based on a  "single industry" pike that hauled coal, a not very glamourous product, 
  • only ran just over a mile on the prototype,
  • only ever had 2 operational steam locomotives at any time in the 50 years of its operational life,
  • was narrow gauge, 
  • was not in the US/Canada,
  • is still small as a model layout in terms of overall footprint when compared to a larger "basement filler" layout
  • has a model train length limited to loco plus 11 small, identical-looking wagons
  • was built using a modified TOMA approach (staged construction of its modules) 
  • was planned for future exhibition use (and I've been told repeatedly here in response to some of  my previous postings that any techniques/approaches used have little or no relevance for a "home build" TOMA-based layout.)
  • probably not of much operational interest because it doesn't use US-based railroading operational practices (because it wasn't in the US? - strange that?)
  • and, was built for a different purpose than a home layout, This layout was built to do more than just "entertain the operators" as perhaps are most home layouts, when the purpose of a home layout is distilled to its essence.

The layout consists of 12 modules and covers a floor area of 23' by 17' (Hmm - starting to get towards a half-way decent sized "basement filler"  layout size). It will not grow any larger, because the logistics of moving and storing a layout of this size that doesn't have a permanent home define the layout size limits.  

Could it grow bigger? Undoubtedly yes. But should it grow bigger? No - this layout is at the limits of what can be easily stored, transported to a venue, speedily set up (in about 1 hour) and speedily dismantled for transport back to storage by a 2 person team.

Any given module can be separated from its neighbours in well under 5 minutes, and, in most cases under 2 minutes if work/running repairs are needed when the layout is together.. When not set up, any module or combination of adjoining modules can be easily pulled from its storage frame to have additional detailing work/running repairs done on it at the workbench. 

So just what did this sectionally-based, phased-build of model coal transportation system end up looking like?

_800x600.JPG 

Yes there is still more to do before this layout is fully exhibition ready, but it is almost there. How much more you see of this layout on here, and the saga of its build, is largely up to yourselves, given what I've listed above this photo,  

Regards,

John Garaty

Unanderra in oz

Read my Blog

Reply 12
Oztrainz

No battle plan ever remains unchanged....CONTACT #3

 No battle plan ever remains unchanged....CONTACT #3

Hi all again, 

In the previous post I'd written

Quote:

But unknown to us, these standard gauge tracks were the start of the next skirmish

Here's how it developed.

so we had printed our pointwork templates in 1:1 scale and the dimensions "looked right", with all the pointwork blades clear of module joints as shown in the photo below

301a.jpg 

The initial thoughts were we could use this flat-bottom rail to scratchbuild our own pointwork, including a double-slip. But after 12 months of no progress because our efforts had been needed elsewhere, developing and test-running other stuff for the narrow-gauge, we "chickened out" and purchased enough bullhead rail and all the turnouts including the double-slip from Peco. If anything, this decision has enhanced the prototypicality of the layout because the real standard-gauge trackwork around the screens was in bullhead rail, including the double-slip. 

Here's the prototype track plan we were trying to model (click for a larger image)

nal30dpi.gif 

When compressed to fit the limitations of module widths and lengths, the Dirt Road trackage was deleted to give the following simplified trackplan schematic within the solid black rectangle (again click the image for a larger size if required)

SG_Final.jpg 

This all looked very good until the tracks arrived. We then found that "things" didn't fit. As originally planned, looking toward the incline ( the 1200mm long incline module is just in shot at left) 

MG_8861a.jpg   

and back towards the screens, 

MG_8869a.jpg  

When it was laid out on the 1:! plan, the double slip has moved ominously close to the end of the extended tipple deck and the associated module joint of the 1400 mm long module. as shown in the photo below

MG_8939a.jpg 

 

This caused problems at the other end of track on the 1200 mm long Incline module, where the headshunt at the left of the top track in the model trackplan above  had effectively disappeared. 

But now we realized that the incline module was incorrect. in that the incline part of the module should be a narrow strip rising to the next module but most of the width of the module should be flat for the standard-gauge empty wagon standage sidings. 

So we built a new longer 1400 mm long Incline module and reworked how the incline part was mounted to the frames.

MG_9086a.jpg 

which gave a headshunt at the far end of the photo that could hold 2 wagons, but put the double-slip on the module joint. Something had to give, and it was the double-slip that was now in the "wrong place" across a module joint.

MG_9076a.jpg 

As I've said previously on here in other postings. You avoid this if you can. If you can't, then you'd want to be really sure about how you are going to do this before you power up the Dremel. If you do it right, then it goes back together OK. But get it wrong on the most expensive piece of trackwork that Peco make, then, it could have got really expensive very quickly...

And to show it all finally came together and how tight that headshunt is. "Are we there yet?? "BUMP!! "Yeah, we're there."

1000879a.jpg 

And we haven't even begun to build any of the narrow-gauge tracks and the incline itself yet,

Regards,

John Garaty

Unanderra in oz

Read my Blog

Reply 1
Oztrainz

No battle plan ever remains unchanged....CONTACT #4

 No battle plan ever remains unchanged....CONTACT #4

Hi all again,

As were are using tables to support the join area between modules, once the incline module was built it became obvious to us that the Top End module at the top of the incline needed better support. The narrower 200 mm deep frame couldn't be successfully joined to the new Incline module  

As originally built, with the shallow-framed Top End module at right of photo.

291a.jpg 

As rebuilt with a deeper frame that allowed 4 hinges as aligners, to ensure first-time, every-time track alignment across the module join.

1000916a.jpg 

Note the 2 extra vertical aluminium RHS pieces. These allow the change in direction to the next module as shown below

800x600).jpg 

Time is now October 2012, just on 7 years since we chose Corrimal Colliery and its incline as the modelling subject. And we still haven't laid any narrow-gauge tracks, but we're getting close...

Regards,

John Garaty

Unanderra in oz

Read my Blog

Reply 1
Oztrainz

Construction concepts - Hinge Theory 101

 Construction concepts - Hinge Theory 101

Hi all again,

One of the key construction concepts behind the Corrimal layout is the use of hinges to maintain structural integrity and track alignment across module joints. The use of such hinges has been used successfully on other exhibition layouts in Australia for at least 15 years that I know of. As such, it made good sense to use a proven module alignment system based around hinges,  

You need to be selective with your hinges, previously at  https://forum.mrhmag.com/magazine-feedback-was-ezines-891776 in the "Joining?" post I wrote:

Quote:
  • For joins between between modules, I'm using hinges that can have the pins removed. The trick here is to get hinges where there is no vertical slop between the halves of the hinge. Be very selective with your hinges. You are relying on them to ensure that gaps can't open up at track level.

As an illustration from the previous post - If you have deep modules, then use hinges at top and bottom to stop the module joint opening up around a single central hinge.

1000994a.jpg 

The hinges are the black bits on the shiny silvery aluminium frames. The deep frame joint in the centre of the photo has 2 hinges on each side as mentioned above (one at the top and bottom). The shallower 90-degree junction at top centre of the photo only has one hinge on each side. 

The same approach using hinges can be used for timber module framing.

Provided you have minimal slack between the hinges and the pins, then the modules will go back to the "same place" every time relative to each other. This helps to ensure that the tracks jumping module joints go back in the same place "first time - every time" and your track alignment is perfect every time the modules are reassembled - whether one time or 50 times. 

This following construction photo shows another benefit of good fitting pins. In the photo below  the pins have not been fully pushed home into the hinges. For the 3-segment hinges we used , the pins only have to be started into the 3rd segment of the hinge to maintain accurate alignment. This makes removing the pins easier if the modules have to be split.

1110796a.jpg 

When fully set up in exhibition mode, the pins are pushed fully home. For home use in a TOMA approach, there is no need to fully push the pins home on a specific module joint until construction and finishing have reached the stage where the need to remove either module for further work is unlikely.

Also in this photo, at the top right, the internally fitted bracing angle that maintain the position of  one of the additional vertical RHS verticals that are used to support the module that diverges to the left in the top photo. This approach avoids weakening the structural integrity of the module, as would have occurred if plastic joiners had been inserted in the main longitudinal members.     

CAUTION - there are some module junctions where using hinges and pins is difficult to do. 

rimalSt2.jpg 

The 4-way junction between the 2 Brokers Nose and 2 Mine Run modules is just about impossible to secure with 3 hinges required in very confined spaces .How we got around that can wait until we get to the construction of those modules.

That ought to do for Hinge Theory 101,  

Regards,

John Garaty

Unanderra in oz

Read my Blog

Reply 1
Oztrainz

The double-slip - A historical diversion

 The double-slip - A historical diversion

Hi all again,

For our model, the double-slip was a "must have" because Corrimal was one of the few places, if not the only place where a double-slip in bullhead rail was used by any industry in NSW. The diagram below has been distilled from various historic references. It represents the general layout of standard gauge track arrangements at Corrimal at the bottom of the narrow gauge incline. The diagram is not to scale.nal30dpi.gif This standard-gauge trackwork including the double-slip, was installed in 1890, when the original 2’ gauge “main and tail” rope incline was shortened and converted to a self-acting continuous-rope incline.  

The following diagram outlines how a "main and tail" type incline operated, with the brakes always slightly dragging on the un-powered drum. This type of an incline could handle an undulating track profile.

n%26Tail.jpg 

The long length of this earlier "main and tail" type incline had severely limited the output of the mine. This new standard gauge railway was intended to overcome the limitations of the earlier incline, by hauling coal away, over the flatter part of the run to the NSWGR connection near the present site of Corrimal station, in larger wagons of about 10-ton capacity. This freed up a large number of the smaller 3/4-ton capacity 2’ gauge coal skips that could then be returned empty to the coal face quicker, rather than being held captive above ground on the longer slower incline. This trackwork was demolished in 1955, after the standard gauge line was diverted to serve a new washery at nearby Tarrawanna, directly below the mine.

The double-slip was used because of the geography of the area. The track layout to the left of the Screens building was tightly constrained by the rapidly rising Illawarra escarpment. This rising terrain severely limited both the length and capacity of the empty wagon sidings to the left of the Screens Building. These empty wagon sidings had to be actually hand-dug to form a valley on the side of the Illawarra escarpment. This link is to a photo from the ocean side of the screens. It  gives some indication of the steep terrain after the Screens, with Brokers Nose dominating the skyline.

The rising terrain also enabled the wagons to be gravity shunted from the empty wagon sidings, through the loading chutes at the Screens Building, and then on to Full wagon sidings to the right of the Screens Building in the top diagram.

After the wagons were loaded, they would be marshalled into trains of 17 un-braked wagons. Loaded trains were limited to 17 wagons after a runaway in the early 1890’s.  

There is only one known blurry photo in existence that shows the double-slip at Corrimal Colliery. This photo is File P12/P12913 from the Illawarra Images on-line collection at Wollongong City Library. This undated photo shows the Corrimal 2’-gauge incline, probably in the late 1890’s/early 1900’s, descending towards the Screens and standard-gauge tracks. Fredrick Danvers Powers is known to have visited Corrimal when both the original Brokers Nose mine and the newer Daylight mine at Corrimal were operational. He gave a detailed account of the manner of working the mines and the equipment in use at Corrimal and on the incline. His book “Coalfields and Collieries of Australia” was published in 1912. That book listed significantly different details of the equipment at the lower end of the incline than those shown in the photo below. The double slip is visible to the left of the group of empty wagons that are parked clear of the Screens Building.   

P12913.jpg 
 Corrimal Screens looking East – From the collections of the Wollongong City Library and the Illawarra Historical Society

This track arrangement also gave Corrimal great flexibility when feeding empty coal wagons to the screens. Most of the market prior to WW2 was for lump coal for industry or export. This was loaded from the upper track under the Screens Building as shown in the previous diagram. These wagons would fill quickly with the larger coal. This track arrangement, with its combination of crossovers and the double-slip, allowed empty coal wagons to be fed to this “lump coal” chute under the Screens from any of the three empty wagon sidings to the left of the Screens.

Surplus empty wagons that could not be fitted into the empty wagon standage sidings could be held to the right of the screens on the uppermost track that passed outside of the Screens Building. This track was the dedicated arrival road for empty wagons. The locomotives always propelled the empty wagons up to the Screens.

Locomotive access was limited to this arrival road and to the empty and full sidings, but was restricted to areas well clear of the Screens Building because of the low clearances under the screen chutes. These low clearances were necessary to minimise breaking up the coal when it dropped into the wagons.   

There was also space between the points on the lower storage track and the Screens Building to hold several wagons uphill of the Screens for the middle and lower tracks under the Screens. The middle track under the Screens was for "nuts" that were smaller sized and were sold for household consumption locally and in nearby Sydney. The loop track closest to the narrow gauge tracks was the "dirt road" for fines. The wagons for the Smalls and Dirt Road chutes would take longer to fill, because of the smaller size of the coal. Corrimal was fortunate in that it had its own cokeworks to dispose of any "unwanted small stuff" that could not be sold. Prior to 1912 the cokeworks was at Unanderra. After 1912, the cokeworks was moved to Corrimal, adjacent to the main railway line to Sydney. Coke  production continued on this site at Corrimal until 2015.

I hope that this helps to both explain why we needed the double-slip, and how it went back together after we'd chopped it in half,

_800x600.JPG 

That'll do for now, next time we go pile-driving,. 

Regards,

John Garaty

Unanderra in oz

Read my Blog

Reply 1
Oztrainz

Pile-driving

 Pile-driving

Hi all,

Now that the standard-gauge tracks are in place and sorted, it was time to work out just how we were going to build the narrow-gauge incline tracks. Start at the top and build down? Or start at the bottom and build uphill. After a fair bit of discussion between us we went with Option B and built uphill. 

We opted to build the tipple deck first, so we started pile driving

1000114a.jpg 

Yes - that's 1/2 of the double slip on the middle track in the distance 

Then we had to fit the aluminium channel to carry the under-track chains for magnetic haulage of the coal skips..  I haven't mentioned that I needed 2 chains through the tipple deck yet. Perhaps I'd better cover that next time..

1000890a.jpg 

So we glued the channel to the inner side of the piles on the side closest to the standard-gauge tracks. This matched the track position shown in the only known photo of the deck, where the track was close to that side of the deck with a narrow walkway and fence between the tipple deck track and the drop to the lower-level Empties track, with its own under-track chain channel to the right. 

But first we had to get that aluminium channel up "The hill". We did a test fit of the channels

1000888a.jpg 

That allowed us to accurately make and glue in a vertical web to support the channel 

1000902a.jpg 

then, glue the channel to this supporting web and secure the channel to the incline floor board

1000903a.jpg 

I'll cover what happens with the under-track channels at the top of the hill in the next post. This post is probably long enough already. And there is still no narrow-gauge track laid yet...

Regards,

John Garaty

Unanderra in oz

Read my Blog

Reply 1
Oztrainz

Going over the top

 Going over the top

Hi all again,

At the top of "the hill", we had to bend the under-track channels so that we got back to horizontal, but finished at 2 different heights, because eventually the Empties Incline track has to cross over the Fulls Incline track, 

BIG TIP - When jumping module joints on a grade, keep the grade constant. Make your grade changes a least a wagon-length beyond the module joint. It is hard enough "keeping everything together" at module joints without adding a grade change into the mix of variables. 

The first track to be worked on was the lower-level Fulls Incline track.

1000910a.jpg 

Note the saw-cuts in the channel. These extend down the sided of the channel to the top surface of the bottom of the channel. This allows the channel to flex vertically. In this photo the supporting web for the channel and the cut through the channel at the module joint is still to be made.  

Next it was the turn of the higher level Empties incline

1000997a.jpg 

shown with the supporting webs in place and the higher-level channel propped in position. 

We then mounted a motor under the tipple deck.

1000998a.jpg 

Fitted a sprocket, set up some return sprockets at the other end and under the deck to manage the chain and had a play

 

 Hey, with some scenery wrapped around this, it might just work...  

But there is still a lot more work to do before the tracks can go in for keeps,

 

Regards,

John Garaty

Unanderra in oz

Read my Blog

Reply 1
Oztrainz

The concept of de-coupling

 The concept of de-coupling

Hi all again,

Previously in the 'Piledriving" post above I wrote 

Quote:

Then we had to fit the aluminium channel to carry the under-track chains for magnetic haulage of the coal skips..  I haven't mentioned that I needed 2 chains through the tipple deck yet. Perhaps I'd better cover that next time..

Well "next time" has arrived. What's all this about a second chain??

On the prototype, at the top of the hill, loaded skips were attached to the haulage cable with clips and the cable took them downhill to the tipple deck. At the tipple deck the skips were unclipped from the haulage rope and manually moved into the tipple cage. The skip was tipped, dropping its load of coal onto an elevating conveyor that lifted the coal into the top of the Screens building, where the coal was mechanically sorted for size and any lumps of coal with too much shale or stone in them were manually removed at a picking table in the top of the screens.

After the skip was tipped, it was pushed clear of the tipple cage and then lowered on a creeper chain, that was also driven by the incline haulage rope, to a lower level. On this lower level the skip  was gravitated back to under the tipple deck where the rope emerged under the tipple deck for its trip back uphill. This marked the start  of the Empties incline track. The clips used on the skips for the downhill run were dropped through a chute to near where the haulage cable started its return run. The empty skips were then clipped to the haulage cable to take the skips  back to the "top of the hill".

This brings us to the concept of "decoupling". The loaded model skips must be "decoupled" from the chains driving the Fulls and Empties incline tracks, because like the prototype haulage rope. if the incline was working these under-track chains that stand in for the haulage cables should never stop. But the skip has to stop so that it can be tipped. We needed a way to "decouple" the haulage operations each way from the tipping operation. 

So we came up with the idea of a second chain under the tipple deck to handle the tipping operation and to haul the skip away after it was tipped

1010002b.JPG 

A closer view showing the tipple, sprocket with chain and support channels 

1010003b.JPG  

This chain was powered by a motor mounted below the baseboard under the end of the kickback.

1010009a.jpg 

Initially we had some concerns that this arrangement would not drive the chain satisfactorily. But once we got this chain running, it became obvious that this type of a mount was good enough to do the job, plus it made swapping out a motor a whole lot easier in the event of a failure than where the motors for the incline chains were initially mounted, directly at the end of the "haul run" on each incline track. So the incline motors were relocated to under the baseboard before scenery work was commenced.

This all looks nice, but we still haven't laid any track yet... 

Regards,

John Garaty

Unanderra in oz

Read my Blog

Reply 1
Oztrainz

Plating the Incline

 Plating the Incline

Hi all again,

for things to progress further we needed to get a smooth surface under the incline track for the magnets on the under-track chains to skate along. 

We opted for stryene and plated each on the modules where under-track chains were running. 

When we were done, we had a white ski-jump that looked like this when viewed from the top of "the hill":

1010253a.JPG 

At the top of the hill. the grade separation and module joint looked like

1010251a.jpg 

At the kickback at the lower end, we had another white ski jump

1010259a.jpg  

but this one had a mouse-hole under it. We'll come back to the mouse-hole later.

This last photo has some track in it that had been modified for the vertical curves at the kickback. Yes the track is finally ready to go down. YAAY!!  

Regards,

John Garaty

Unanderra in oz

Read my Blog

Reply 1
Oztrainz

Styrene Heave

 Styrene Heave

Hi all again,

Even before tracklaying commenced, we observed some "strange stuff" happening with the stryene track foundations that covered the under-track channels. To keep this all together and to save a lot of re-typing I'm adding an edited version of a previous post elsewhere on here. 

If you can build your layout in a climate-controlled environment, then you might be OK, but the expansion properties of track and stryene appear to be significantly different from my experience. But a build under climate-controlled conditions wasn't an option for us - because we were building outside in either Guy's backyard or my driveway.

The following photos show the incline module and some of the expansion difference problems we had. This layout uses 2mm thick styrene sheet over an aluminium U channel (to carry the under-track chain with magnets attached used to move individual coal skips) with the tracks secured initially by glue and later with the track secured by PCB strips and screwed to timber blocks surrounding the channel. The under-track magnets being towed by the chain slide along the underside of the styrene when there is a coal skip being towed.  

Photo 1 - As originally built, showing a styrene "heave" under the lower level track, This was just one of several heaves over the length of the first 3 modules. Timber blocks ether side of the channel are secured to a solid MDF foundation sheet that is bolted to the aluminium module frames.

1010243m.jpg 

Photo 2 - Incline module as rebuilt with extra timber blocks and securing screws, But even then, both tracks have been displaced sideways due to stresses. The trackwork was functional for one-skip-at-a-time up and down the grade. This led to the next rebuild.

1010312m.jpg 

Photo 3 - Incline module with track rebuilt and secured with PCB strips. This time the tracks stayed straight. This was the 3rd time the incline trackage with styrene had been re-worked.

1110374a.jpg 

From what I've seen, I'd be very wary about going to a styrene-based module because of the different expansion rates between long lengths of styrene, track, and other supporting structures. But because we had the under-track chains with magnets, we NEEDED the styrene between the track and the chain channels

See, I knew there was a really good reason why we didn't immediately rush into scenery construction as soon as the tracks went down.    

That's probably more than you ever wanted to know about styrene-induced track heaves,

Regards,

John Garaty

Unanderra in oz

Read my Blog

Reply 0
Craig Townsend

Strips vs. Sheets

Strips vs. Sheets

John, I'm assuming that you bought the styrene is large sheets? I wonder if in the manufacturing process, or in the cutting of smaller strips some of those stresses are alleaved. Do you remember what the total weight of the modules was around this time? Keep up the posts. I find them very interesting and very well thought out. Craig

Reply 0
Oztrainz

For Craig

 For Craig

Hi Craig and all,

The stryrene was purchased in a large sheet. I can't remember the size of the sheet (6' by 4'?).

As for module weight:

We didn't weigh the modules while they were at "bare bones" stage, so I don't have definitive weights for these first 3 modules as shown in the photos  in "Plating the incline" thread above.

The bare aluminium frame comes in at about 5kg or  about 10 lb all up for both the 1400 mm long and 1200 mm long modules. The solid timber top adds about another 3 kg to the weight. The track support structure probably adds about another 1 to 2 kg absolute maximum to the weight of each of these 3 modules. Scenery would add another 2 to 3kg (light-weight scenery used).

The module with the screens and tipple buildings on it would probably come in slightly heavier than the other 2 modules. I would expect any of these 3 modules to weigh in at less than 15 kg (30 lb) when completed with scenery. Although the extra mechanisms and buildings on the Tipple module might add enough extra weight to just go slightly heavier than this. 

But a 1200 mm long module with scenery comes in at 12.6 kg (about 28 lb) complete. The photo below shows the digital scales with the module upended on it.

1180797a.jpg 

 I hope that this answers your questions satisfactorily,  

Regards,

John Garaty

Unanderra in oz

Read my Blog

Reply 1
Oztrainz

Build your own coal skips - Part 1

 Build your own coal skips - Part 1

Hi all again,

While we were working out how to build this layout we also had to work out how to build what would run on it. That included the coal skips that would run on the incline between the mine and the tipple.

In the real world the coal skips looked something like this:

from the side -

1000328a.jpg 

and from the end, showing the drawhook and dumb (unsprung) buffers:

1000327a.jpg  

The centre band with the loop is a harness attachment point for when the skips were moved by pit pony, There is a similar loop on the other end. But photos of the Corrimal skips show all timber skips were without that band, so the drawhook between the buffers was used at Corrimal for horse haulage. 

Although these skips hold 3/4 ton of coal, they really are quite small - on 2' gauge with 12" diameter wheels. 

Here's what they might have looked like when new 

1000360a.jpg 

The philosophy of model coal skip building will continue after we get some track down on the first 3 modules - That's up next, 

Regards,

John Garaty

Unanderra in oz

Read my Blog

Reply 1
Deemiorgos

John, have you figured out

Small wheels?

John, what did you use for those small wheels? Will you be changing them.

Reply 0
Oztrainz

For Deem - re wheels

 For Deem - re: wheels

Hi Deem and all,

It took a fair bit of work on our part to get the wheels we use on the model coal skips made specifically for us. At the time we needed them, scale-diameter 6-spoked wheels around 7 mm (about 1/4") diameter with HO wheel profiles simply were not available. So I'm not sure why we'd change them?? 

I'm sure all will be come clear after we get into the finer points of model coal skip design soon. However to add to the anticipation, for anyone who has never seen a 3-link coupling, drawhooks and dumb buffers in action, here's a photo of how things look between 2 coal skips. 

213a.jpg 

When being pushed, as shown in the above photo - the train forces are transmitted through the wagon frames when the dumb buffers bump up. This allows the 3-link coupling to go slack and be flexible, preventing tangling when going around tight curves.

 When being pulled - the train forces are transmitted though the 3-link coupling. As the coupling stretches out, the dumb buffers separate and the 3-link arrangement allows enough flexibility to handle track irregularities and any curves. 

In the words of a past TV show and current movie franchise -

"Your mission, should you choose to accept it, is to be able to couple and uncouple 1/43rd scale coal skips at desired locations without the availability of 1/43rd scale workers to 'flip the links". This message will self-destruct in..."  

Let me know how you go, 

Regards,

John Garaty

Unanderra in oz

Read my Blog

Reply 1
Craig Townsend

Magnets?

Magnets?

Well seeing how magnets solved one problem, maybe they can solve two? Craig

Reply 0
Oztrainz

Too many...

 Too many...

Hi Craig, 

You will need a Plan B. Magnets were ruled out for for couplings very early on. 

To misquote a quote about superfluous culinary masters and sub-quality soup -

"Too many magnets (in too little space) spoil the flux".

All will be soon made clear...

 

Regards,

John Garaty

Unanderra in oz

Read my Blog

Reply 0
Oztrainz

Track laying - end Part 1

 Track laying - end Part 1

Hi all again,

After we'd dealt with the styrene heave problem for the first time, the the modules were re-plated with enhanced under-pinnings to hold everything down and solid. Our first attempt at tying the track down with hot glue had proved less than successful in the heat of an Aussie summer.

A caution here to anyone using hot glue to hold stuff down or together - prolonged exposure to direct sunlight is NOT a good idea. You might get a nasty surprise at just how quickly stuff heats up to an unacceptable level where stuff that was glued starts to come unstuck, BTDT...

Prior to track relaying, a combination of balsa and stirrer sticks were stained for the use tipple deck and other structures such as retaining walls. The following photo shows the staining "assembly line" in full swing, with freshly dunked stir sticks laid out for drying.

1010290a.jpg 

Various amounts of the raw stock was dunked into a bath using 3 different strengths IPA/india ink by increasing the amount of ink added and topping up the IPA level to make up for absorption losses from the bath.. At each bath concentration level, 3 different dunk durations were used. This gave us a range of tints.    

Track laying started at the far end of the kickback siding and worked back uphill using a solvent type glue to glue the plastic sleepers to the sub-track styrene plating. This time the track stayed stuck.

 1010292a.jpg 

The decreased spacing of screws indicate the presence of vertical curves where more hold down effort is required to prevent the track and plating from moving. 

And a bit further along on the lower level

1010301a.jpg 

The following photo shows some of the stained sticks and balsa laid out on the tipple deck to give us a feel of what a completed tipple deck might look like..

1010306a.jpg 

The hole in the deck is where the tipple house sits (when it got built) . But there was a smaller hole within this hole - the space where the yet-to built tipple mechanism has to fit. 

And it is a chicken and egg situation - the tipple design can't be finalised until the design of the coal skips is fully nailed down - Remember that previous posting about "Build your own skips - Part 1"? Well, Part 2 of the saga will be along shortly.  

Track building then stalled at the top end of the plating - while the incline chains and skips were tested intensively. 

 1010603a.jpg 

The top end module was where we leaned how well we eventually had to tie the track down to avoid styrene heave. 

1010601a.jpg 

This method also got around any glue failure problems between the styrene and the track. 

Much later the incline module and parts of the Tipple module would be rebuilt in a similar manner. 

More next time,

Regards,

John Garaty

Unanderra in oz

Read my Blog

Reply 1
Craig Townsend

IPA

IPA?

Am I the only one that read IPA as India Pale Ale? Beer must have been on my mind. I know what it really stands for... Craig

Reply 0
Oztrainz

If...for Craig

 If...for Craig

Hi Craig,

If you want to mix ink with your beer that's fine by me  

But I probably wouldn't recommend it. That might stain your teeth 

Regards,

John Garaty

Unanderra in oz

Read my Blog

Reply 0
Oztrainz

Build your own coal skips - Part 2

 Build your own coal skips - Part 2

Hi all again,

It's been a while. So on to the nitty-gritty of building 1/43rd scale 2' gauge coal skips. 

The Mark I coal skip   

Our first attempts on the test rigs were simply HO bogies with magnets attached - simply to prove the concept of using magnetic haulage to represent wire-rope haulage on a steep grade. Remember the Mark 1 Test Rig?

These worked pretty well and allowed us to proceed towards something that looked more like a coal skip. Enter the Mark I coal skip

068a.jpg 

These Mark I coal skips used cheap 10.6mm diameter wheels. Magnetic couplers such as Kadee or Sergeants were ruled out because the steel in the couplings interfered with strong under-track magnets used on the incline chain .  So we opted initially for some cheap Lima couplers. With these were able to prove that ramp type uncouplers would work as shown on the lower level in the photo above. To see how the Top End works, may I offer a reprise of the test rig above shown in action with Mark I skips? 

 The Mark I skips were also used to test possible track layouts for the Tipple module and for the initial tipple "tipper-outer" trials. 

218a.jpg 

I'll cover some of the construction details of the Mark I coal skip and its development into the Mark II coal skips next. 

Regards,

John Garaty

Unanderra in oz

Read my Blog

Reply 1
Oztrainz

Decoupling 2 - controlling the Bottom End

 Decoupling 2 - controlling the Bottom End

Hi all,

Skip design will be resumed shortly, but first another "diversion" into animation/automation that enables hands- free operation of the Tipple...

Previously the prototypical operations of the narrow-gauge tracks at the foot of the incline were discussed in "The concept of de-coupling" post on the previous page. This mentioned the 3rd under-track chain but didn't go too much into how we set it up for "hands free" operation.

I'm not sure whether this is classed as animation or automation. Sometimes the dividing line between the 2 can get pretty thin.

The automatic controls for starting the chain under the tipple when a skip arrives, stopping the chain with the skip in the tipple cage, triggering the tip cycle and restarting the chain after the skip is tipped for hands-off operation of the bottom-end of the incline were purpose-designed by team member Mike Milway. These controls were built in 2012 for the 2013 Australian Narrow gauge convention and performed well during the convention once we got the tipple itself sorted (but that's another war story for a different time). This circuit also has a built-in delay that prevents the tip cycle from re-arming until the skip is well clear of the cage.

How the tipple sequence works:

For scenic purposes there will always be 3 full skips waiting on the deck outside the tipple house. These skips will be kept uncoupled by a ramp between the rails. This ramp will also be the exit point for the non-operational haulage rope for the Fulls Incline that brings loaded coal skips down hill. 

  1. A loaded skip arrives off the incline and pushes the skip immediately outside the tipple house into the tipple house.
  2. A reed switch under the track just inside tipple house detects the magnet on the skip and starts the chain under the tipple house floor.
  3. When the magnet on the chain arrives at the skip, the skip is towed to the tipple cage.
  4. Another reed switch under the tipple cage detects the magnet on the chain and skip, stops the chain, and triggers the tip cycle. Once the tip cycle is triggered, this reed switch is disabled by a timer to ensure that the tipple doesn't try to tip again while the empty skip is leaving the cage.
  5. The tip cycle is timed so that the skip will reach the tipped position, then hold for about a second before returning to its start position aligned with the tracks. A delay of about another second is programmed in so that the cage is "known" to be back before the under-floor chain is restarted, towing the skip away from the tipple cage
  6. The skip is towed away to the kickback points. As the skip approaches the blades on the kickback points, the route is set by a servo to the straight path towards the dead end.
  7. As soon as the wheels of the skip clear the blades, the magnets on the chain and skip are sensed by another reed switch, and the route is set to the diverge path leading to the start of the uphill Empties incline at a lower level than the tipple.
  8. The dead end is on a rising 1 in 7  (14%) grade. When the magnet on the chain rolls around the sprocket at the upper end of the dead-end, the magnet on the chain loses attraction to the magnet on the skip. Gravity takes over and the skip rolls away to the start of the Empties Incline
  9. The skip has to roll far enough beyond the start of the under-track Empties Incline so that the next magnet arriving on the Empties Incline can attract the skip and tow it away uphill to the top of the incline.
  10. After rounding the sprocket at the top of the dead end, the link carrying the magnet continues back under the deck toward the tipple house
  11. Just before the sprocket under the parked skips there is another reed switch that senses the magnet on the chain. This reed switch stops the chain and everything waits for the next skip to arrive in step 1 and trigger step 2. It takes just under a minute from the time the chain start at Step 2 until it stops at Step 11.   

So now you know why it took just on 12 months to get the control circuitry designed and built so that it operated reliably enough for hands-free operation....And just to prove it all worked as designed

BUT... we have a problem

The circuit was originally built using 555-timer chips about 5 years ago. Last outing we had a couple of unexplained glitches. Last week the problems got worse with erratic performance for varying random periods. After a fair bit of trouble shooting, it looks like the control panel has problems with a poor solder joint/broken wire/corroded circuitry or perhaps even all 3 somewhere in one or both control boards.

That'll do for this post. Plan B is next.  

Regards,

John Garaty

Unanderra in oz

Read my Blog

Reply 1
Oztrainz

De-coupling 3 - Have Arduino, will program...

 De-coupling 3 - Have Arduino, will program...

Hi all again,

Looking at the 2 control panel boards running this circus, additional troubleshooting could burn more time that we don't have, The servos and the servo controller driving the 2 servos appear to be OK and are functioning as designed. So I need a Plan B.

Here's the thinking so far: 

 Defining the equipment

ChainHome - the reed switch that stops the undertrack chain at the end of the tip cycle

SkipArrive - the reed switch that starts the tip operations cycle - Starts the under-track chain

Cage - the reed switch under the tipple cage. This stops the under track chain and triggers the tipple servo that tips the coal from the skip.

KickbackApproach - the reed switch that triggers the kickback point to accept an incoming empty skip from the tipple 

KickbackDivert - the reed switch that sets the kickback points to the divert route after the skip wheels have cleared the blades 

CageServo - the servo that drives the tipple cage

KickbackServo - the servo that drives the kickback points.

Complications

The magnetic flux pattern changes as the skip rolls past a reed switch. Effectively there is zero magnetic flux and the reed switch will open if the magnet is centred directly over the reed switch. So once a field is sensed, we want the control circuitry to "stay switched" unless instructed otherwise. 

Consider the kickback points. The ANE Smartswitch controller is currently set up so that a second signal on the same reed switch causes the same outcome as the first signal = No subsequent motion, because the reed switch has already triggered the move. so   

At start-up - the first skip arriving from the tipple will set the direction of the turnout through the KickbackApproach reed switch. Prior to that first skip arriving, the orientation of the kickback turnout simply doesn't matter . Once the first skip arrives the circuit is self-correcting provided that the reed switches work. 

There is also the problem of starting and stopping the under-track chain at different locations on demand. This is powered by a 12V gearhead motor that can pull up to 1.4 Amps.

The Plan B                                                                                                                               

Replace the control circuitry with an Arduino and use it to feed the "go" signals to the ANE Switchmaster that controls the speed and travel of the tipple and kickback servos. This part of the control system is working OK and looks like it does not have to be replaced.

The Arduino should be able to replicate the 555 timer inputs as part of the internal programming in Arduino-speak..

Implementing Plan B

So I bought an Arduino... and was able to load Dr Geoff's "Rotating Beacon" program into the Arduino, solder a resistor and a LED to some header wires.... and then got an LED that flashes as specified. 

If I use several switches to stand in for the various reed switches, and assign them to some Arduino pins - that's the easy bit.   

Now if I can pick the "right bits" of code and the shotgun them into the correct order into an Arduino sketch...

If I can get the Arduino to simulate the operations of the old control system, then it should be a case of unplugging the old control system, modifying the reed switches and ANE Switchmaster plugs to match the Arduino connections and then powering up the Arduino.

Hey - If I can get an LED to flash by Arduino, in the words of a former BBC motoring presenter "How hard can it be???"

Now would probably be a good time for some of the resident Arduino experts on here to chip in with some advice..   PLEASE!!!    

Come back next time for Programming Logic 101. It will be along shortly                                                                                   

Regards,

John Garaty

Unanderra in oz

Read my Blog

Reply 0
Oztrainz

De-coupling 4 - Programming Logic 101 - Understanding reality

 De-coupling 4 - Programming Logic 101 - Understanding reality

Hi all again,

Before you write a programme in Arduino-ese, it helps if you know what you want to achieve. In this case I want an Arduino that will do what my older 555-based control system did. So before we go to Arduino-ese, lets look at the defined equipment in the previous post. Consider a series of "cases', which are unique circumstances where stuff might have to happen.

To assist my understanding and to establish some ground rules for the various reed switches:

  • if no magnet is "near" the reed switch the switch is open and no voltage flows through the reed switch = HIGH
  • if a magnet is "near" the reed switch, the switch is closed and voltage is able to flow through the reed switch = LOW 

There is only 1 magnet on the under-track chain driving the tipple operations. The speed and travel of both servos have been defined and are controlled by the Smartswitch board. 

CASE 1 - Set up - with magnet at ChainHome 

This sets ChainHome LOW and all other reed switches are HIGH. The chain does not move. This is the "preferred" starting position. Cases 2 and 3 will both end here.

Case 2 - Set up - with magnet away from ChainHome.

Chain will start and continue until it reaches Chain Home. It upstream of the tipple the magnet on the chain will activate Cage, KickbackApproach and KIckbackDivert reed switches on the way past. This would "prove" that all parts of the tipple operation are functioning without hauling a skip through the system. 

Decision Required -  Is it a good idea to replicate the operations in Case 3 by forcing a test run without a skip at power-up as part of SetUp? If ChainHome is specified as HIGH in Setup, this should start the chain whether the magnet is there or not? The magnet on the chain would then trigger all downstream reedswitches, thus proving the system.

Case 3 - Operations - with magnet at Chain Home and the operation is triggered by the magnet under a skip arriving off the incline activating the SkipArrive reed switch

  1. ChainHome and SkipArrive are LOW and all others are HGH - chain starts 
  2. As soon as chain starts ChainHome goes HIGH, but SkipArrive remains LOW
  3. when the magnet tows the skip away, the SkipArrive goes HIGH
  4. when skip and magnet reach the tipple cage and CAGE goes LOW:
    Stop chain, start tip sequence - Set TIPTIME = 0 (in seconds) 
  5. At TIPTIME = 0 send "Tip" signal to Smartswitch board. Servo under cage commences to move
  6. At TIPTIME = 3.5 approx, servo reaches end of travel and skip is at "tipped" position
  7. At TIPTIME = 4.0, remove "Tip" signal to Smart switch, Servo begins to return.
  8. At TIPTIME = 7.5 approx - cage has returned to "Home" position and rails in cage are aligned with those on tipple deck. The skip should be able to exit cage without derailment. Set CAGE to HIGH to prevent the Cage re triggering the tip cycle as the skip is removed from the cage.
    Question Do  I need a shorter DEBOUNCE here for CAGE of about 4 seconds or should I apply a longer one of about 10 seconds once the tip cycle commences??
  9. At TIPTIME = 8, start chain, Skip is towed from cage and heads towards the kickback.
  10. On approaching kickback turnout blades - KickbackApproach goes LOW and sends a signal to Smartswitch The Kickback servo goes to straight path through the kickback turnout
  11. After clearing the blades KickbackDivert goes HIGH and sends a signal to Smartswitch that sets the Kickback servo to the diverge path.
  12. when the magnet reaches ChainHome - ChainHome goes LOW and stops the motor driving the chain.
  13. Tip cycle is complete - the chain is stopped awaiting the next SkipArrive input 

Now to translate all this into Arduino-ese...and to create a testbed that will mimic the required operations. 

Regards,

John Garaty

Unanderra in oz

Read my Blog

Reply 0
Oztrainz

De-coupling 5 - Setting up the testbed

 De coupling 5 - Setting up the testbed

Hi all again,

It looks like a few people are actually reading this saga. So here's the next bit. - setting up the Arduino testbed. 

Initial thoughts

  1. I have a 2.5A 12VDC wallwart powering the the existing control circuitry. It should be more than sufficient to drive the Arduiono from the power input socket. 
  2. I have a similar wall wart powering all 3 chain drives. It has proved more than satisfactory so far. This electrical separation also  helps to keep motor noise out of the control system. The speed of all 3 chain drives is controlled by individual potentiometers in the line to each motor. 
  3. The tipple chains are designed to run continuously and are unaffected by the changes to the control circuitry. The 3rd chain under the tipple is designed to run intermittently under this control system (remember De-coupling??) 
  4. I also have a Servo/Motor controller module for the Arduino,  Whether I can use this is problematic because the Jaycar gearhead motor driving the chain can pull up to 1.4 Amps at peak load and is rated at 0.7A under no load. The servo/motor controller module is rated at 0.6A with a thermally-protected max rating of 1.2A. The requirement for the 2 servo outputs is current managed by the existing ANE Smartswitch servo controller. In service the chain will be in almost continuous motion, because the rate at which skips can be sent down the incline is limited by how quickly they can be tipped and the magnet on the chain gets back to the ChainHome reed switch. Perhaps an easier way is to use the Arduino to trigger a 5V relay in the line between the potentiometer and the motor rather than trying to drive the motor directly via the Arduino. he heavier starting currents and max-rated running currents are then handled by the relay contacts and not by the Arduino directly.
  5. I have 5 Reed switches, Their operation can be simulated by a toggle switch and powered from the Arduino's 5V supply. Reed switch inputs are either on or off and do not require the PWM capability of some Arduino pins. 
  6. I can use LED's to simulate the presence of an outgoing control signal. Lit = signal present - off = no control outgoing signal present.

Initial Hardware Set-up

  • ChainHome reed switch - Pin 2 - to motor relay - Stop if LOW else HIGH
  • SkipArrive reed switch - Pin 4 to motor relay - Start if LOW, else ignore
  • Cage reed switch - Pin 7 To Smartswitch (stop when "tipped time" plus added "surety delay" timed out) and motor relay (stop until timed out) 
  • KickbackApproach reed switch - Pin 8 to Smartswitch (set straight path)
  • KickbackDivert reed switch- Pin 12 to Smartswitch (set divert path)

What have I missed?? 

Regards,

John Garaty

Unanderra in oz

Read my Blog

Reply 0
Oztrainz

This might not be as easy as first thought,,,,,

 This might not be as easy as I first thought...

Hi all,

 I think I need to work on my breadboarding skills a little. These solderless breadboards ain't as easy as they are cracked up to be. 

In under 1/2 an hour last night there were 2 episodes of magic smoke release.  

At present the Arduino is still running, but it is running on a wing and a prayer, One motor and a one wing is definitely shot. I can see the bullet holes in one of the components on the Arduino board.  

But the power input board that came with the breadboard looks like it has had a TSI (terminal smoke incident).

For the Arduino the power input socket is now non-functional (a polite way of saying KAPUT) but the Arduino still blinks on, now powered by the USB from my laptop.  I suppose that I can still reprogramme this board once I've worked out what I want to tell it and use it as a testboard for the programming. And then copy the programme to a new fully functional Arduino that will go under the layout.

All I was trying to do was transfer the blinking diode from pins 13 and 14 on the Arduino to the breadboard and put a manual switch in line with the LED. Nothing as complicated as trying to get a servo to move from here to there or anything like that..

And I still haven't even started to work out the Arduino reprogramming to identify which switch is which...

I can see this getting real expensive real quick if these magic smoke incidents continue at the same rate.   

I'm feeling a bit like the lookout on the bow of the Titanic, running full speed into a sea of icebergs. If there's an ice berg out there, then I'm going to hit it first...But I'm a hard-headed type who has converted a lot of icebergs to ice-cubes over the years,

Pass me the Scotch. The way this is going, I'm going to need it to alleviate the pain involved... 

Regards,

John Garaty

Unanderra in oz

Read my Blog

Reply 0
Reply